Question: 
Mr. Jamal employed 50 workers to finish a work within 30 days. After 20 days he found out that only 50% work had been completed. How many additional workers would be need to finish the task in scheduled time?
50
40
None
50
60
Answer: 
50
Last Updated: 
08/11/2021 - 03:24